| |
 |
 |
 |
 |
 |
 |
 |
 |
 |
 |
 |
 |
 |
 |
 |
| |
| |
| Copyright © 2001 |
| C-Risk, Inc. |
| |
| |
|
|
| |
|
|
|
|
Owner Controlled Insurance Programs - Part 2
David L. Grenier
OCIP - Program Controls
There are a number of compelling reasons why an
owner would consider an OCIP an appealing insurance and risk management
approach, in comparison to a conventional insurance program. Some include:
- Coverage Quality. An owner can mandate minimum
insurance requirements, but it is very difficult to ensure that these
requirements are met. Certificates
of Insurance, the typical method of verifying coverage, provide only
summary information. In
comparison, an OCIP ensures that an owner's requirements will be met. Owner’s can also secure broader
coverage under an OCIP by leveraging the premium volume with an insurer.
- Insurance Limits. Many contractors, especially
smaller firms, carry only $500,000 to $1,000,000 of general liability
insurance. These policies respond
to liability arising from a contractor's work on all of its projects.
However, their aggregate limits may be eroded by claims on projects other
than the owner's. These coverage
limits may be inadequate given today's multi-million dollar settlements
and jury awards. Under an OCIP, an
owner can provide $100 million or more of dedicated liability coverage if
required.
- Insurer Stability. On an OCIP, there can be over
100 contractor and subcontractor firms on a large project, and
theoretically, there could be as many as 100 different insurers covering
these contractors and subcontractors. In addition, all of these insurers
may not be financially stable, and even if all these insurers were at the
start of the project, there is no guarantee that they will remain solvent
throughout the project’s total duration. Under an OCIP, an owner has
direct control over the selection of an insurer and can monitor insurer’s
performance and financial solvency. Typically only one insurer is selected
for the primary workers compensation and CGL lines of coverage.
·
Program Innovation. There has been an increasing interest by owners over the last few
years to use integrated risk management and risk financing methods to augment
the benefits of design-build project delivery on construction projects. This type of innovative risk-transfer
methodology is best utilized on the larger multi-discipline, multi-year, OCIPs,
and requires a strong project management team to administer. Some of these
programs can integrate insurance coverage for professional design,
environmental remediation, force majeure perils, and builders' risk.
Capitalizing on the leverage created under an OCIP approach, an owner can buy
broader coverage at reasonable prices, realizing volume discounts from the
economies of scale.
However,
proceed with caution because these cost savings can be offset by the additional
administration costs. In addition, it becomes more difficult from a claim
perspective when you try top combine P&C policies that are typically
written on an occurrence basis with professional and/or environmental policies
that are normally written on a claims-made basis.
OCIP – Loss Control
& Claim Management
With
an owner assuming significant risk under an OCIP, two important
benefits of this approach are improved loss control and claim
management, both minimizing the cost of retained losses.
- Loss Control. Complementing
the contractor’s existing safety program, an OCIP can help to
standardize safety procedures on the whole jobsite. Also, an
owner can add additional safety staffing, implement a financial
safety-incentive program, expand periodic audits, or some
combination of these options, using the money from contractor
and subcontractor bid credits and insurance deductions.
- Claim Management. Workers
compensation reform in several states over the past few years
has greatly improved employer’s control over injured-employee
claim management. Cost control techniques, such as directing employees to
Preferred Provider Networks (PPOs), return-to-work and
modified-duty programs, and medical bill reviews, can
potentially reduce an employer’s workers compensation costs by
as much as 30%. Owners can offer these program features to all
contractors and subcontractors on the OCIP. This is an advantage
to smaller contractors, since most would not normally benefit
from these features through their individual insurance programs.
Another
claim-related benefit of an OCIP approach is the streamlining of
general liability claim management.
Under a conventional approach to project insurance, the
owner, contractor, or subcontractor, involved in a claim is likely
to be represented by different insurers and attorneys.
An OCIP helps to mitigate and lower the cost of claims
because typically only one insurer provides insurance to all parties
enrolled in the OCIP.
OCIP
– Implementation & Administration
OCIPs
should proceed through the following steps prior to implementation:
·
Feasibility
study.
An important first step to any successful OCIP is the
feasibility study, which is used to evaluate the advantages and
disadvantages, statutory and regulatory impediments, cost savings,
timing and other issues associated with the owner’s OCIP.
·
Request
for proposal (RFP).
Assuming an OCIP is feasible, proposals should be obtained
from brokers and/or OCIP administrators.
In many cases, the broker is the OCIP administrator. However,
it could also be an owner’s representative or risk management
consultant. The RFP should describe the scope of the construction
project, anticipated
OCIP coverage's and requested services, and obtain information from
the broker and/or OCIP administrator about:
-
Background
of the firm.
-
OCIP
administration services.
-
Experience
and location of the project team.
-
Approach
to structuring an insurance program
-
Available
safety and loss control services.
-
Available
claim management services.
-
Computerized
risk management information systems (RMIS).
-
Fees
for all other required service components.
- Interview
process. Firms that submit the best proposals should be
interviewed (or, as they say in the business, invited to the
beauty contest). The firm that can offer the best OCIP
structure, services, innovative approaches, and fees will
ultimately be selected.
- Insurance
placement. The selected firm will work with the owner, and the
contractor if selected at this time, to compile underwriting
information and negotiate insurance terms.
- Document
Preparation. These include the OCIP administration manual, drafting
of the bid document clauses, enrollment forms and similar OCIP
administration materials.
Services and fees can vary widely between firms. Evaluate fees carefully
and negotiate changes where appropriate. Request brokers or OCIP
administrators to submit sample service contracts. Most firms should provide them with the RFP. Negotiate
changes to meet your requirements.
OCIP administration is the critical component to a successful
implementation.
Once
an owner commits to an OCIP approach, there are several things that
will influence its ultimate success, which include:
·
Owner-Contractor
Partnership.
At the onset of a construction project, it is
essential that the contractor, i.e., GC, understands and accepts
responsibility for his or her role in the OCIP program management.
The GC typically has authority over, and responsibility for, the two
most important elements of an OCIP's financial success; negotiating
insurance credits with subcontractors, as part of the procurement
process, and project site safety.
·
Program
Design. To maximize support on the OCIP from the owner and
GC, it is important that OCIP procedures be designed in alignment
with the owner's and GC’s existing practices. The broker, OCIP
administrator, or risk management consultant providing design and
implementation consulting on the OCIP should consider mapping the
owner’s and GC’s procurement, accounting, safety, and risk
management processes and procedures in order to minimize any changes
imposed by OCIP implementation.
·
Information
Management. Every
contractor’s and subcontractor’s understanding and compliance
with OCIP procedures is essential for the OCIP program's success.
Bid instructions and expectations must be clearly delineated and
communicated to all contractors in order to maximize the insurance
deduct process. Timely and accurate claim reporting is necessary to
ensure that all injured employees receive immediate medical
treatment and assigned to a back-to-work program.Timely and accurate
payroll reporting is necessary to measure program financial
performance and ensure compliance with insurance statutory,
regulatory and audit requirements.
·
Documentation and Procedures.
Understanding the requirements and expectations of an OCIP is
accomplished through a number of tools:
-
Easy
to read and understand bid deduct form,
-
Easy
to read and understand OCIP procedures manual,
-
Comprehensive
safety and loss control manual
-
Clear
and concise claim reporting forms and procedures, and
-
Pre-bid
and pre-mobilization meetings and associated documentation packages.
·
Safety
Program. To minimize OCIP losses, it is essential that the
GC create and continually reinforce a proactive safety culture. Most
GCs would do this regardless of being involved with an OCIP or not.
A good safety program has many of the following characteristics:
-
Formalized
safety program and written safety manual,
-
Contractor
and subcontractor safety prequalification procedures,
-
Safety
training, monitoring and periodic toolbox talks,
-
Independent,
scheduled and unscheduled safety audits,
-
Full-time
safety representative and onsite safety staffing,
-
Safety
orientation and indoctrination procedure, prior to mobilization, and
-
Drug
and alcohol testing program.
- Program Monitoring.
An OCIP monitoring program will provide timely
measurement and recording of trends and events that will
indicate program financial results, administrative procedures
effectiveness, and individual contractor safety performance.
These types of reports should be produced monthly, be easy to
read and interpret, and be written in terms that are consistent
with the owner and GCs procedures and expectations.
Key implementation and administration tasks include:
- Prepare
an OCIP manual providing contractors and subcontractors
information about implementation procedures, insurance coverages
and limits, safety programs, claims reporting, record keeping
and other OCIP requirements.
·
Prepare
insurance clauses for bid documents and contract administration.
- Provide
contractor and subcontractor OCIP orientation notices and
meetings.
·
Obtain
contractors and subcontractors evidence of insurance purchased that
is not provided by the OCIP, e.g., commercial auto liability and
general liability DIC coverage for accidents that may occur away
from the project site.
·
Enroll
all contractors and subcontractors in the OCIP.
- Prepare
claims administration procedures for insurers, or claims
administrators
·
Review
contractor and subcontractor bid deducts for all OCIP-provided
coverages.
·
Review
initial bids and change orders to ensure proper insurance
deductions.
·
Collect
payroll and other required reports from contractors and
subcontractors.
·
Prepare
cost reports that show cost of the OCIP and contractor and
subcontractor insurance bid deductions. This will allow the owner to
monitor OCIP savings.
·
Provide
periodic cost reports to the owner, or other owner-designated
recipients.
·
Ensure
that statutory workers compensation reports are filed with rating
bureaus.
·
Ensure
that contractor and OCIP insurers accurately complete payroll
audits.
·
Following
a contractor's or subcontractor’s completion of work, review
performance, quality, and calculate final insurance deductions for
each contract prior to final payment.
NOTE:
It is highly recommended that you review the capabilities of
the risk management information systems (RMIS) used by
administrators to track contractor and subcontractor bid deductions
and fixed OCIP costs. Some of these systems do not track losses and
variable costs. If an OCIP premium is loss sensitive, the total OCIP
costs may require a manual calculation.
Carefully consider this for OCIP reports, and selecting a
broker and/or OCIP administrator.
OCIP
- AUDITS
OCIPs are usually implemented by owners to achieve improved safety,
reduced losses and specific financial results. OCIP administration
requires that the owner’s OCIP administrator complete all
specified tasks for the successful implementation and administration
of an OCIP. Periodic
OCIP audits provide a check to ensure that the quality of OCIP
administration and the potential OCIP savings are being achieved.
Audits should be done on an annual basis, preferably at the same time
each year prior to the anniversary date of the OCIP, and also at the
completion of the project. Items to be reviewed during an OCIP audit
should include:
- Practices
and procedures used for binding insurance coverage, issuing
certificates of insurance, and issuing insurance policies to
contractors and subcontractors.
- Practices
and procedures used for OCIP contractor and subcontractor
enrollment.
- Practices
and procedures used to collect contractor and subcontractor
exposure data, such as experience modification rates (EMR), and
other information required to calculate bid and change order
deductions for OCIP-provided insurance coverages.
- Practices
and procedures for verification that all required OCIP forms and
documentation have been obtained from contractors and
subcontractors, is completely and accurately filled-out, and is
properly filed and maintained by the OCIP administrator.
- Practices
and procedure for WC and GL claims reporting, quality of claims
handling, and administration services provided to contractors
and subcontractors enrolled in the OCIP.
- Practices
and procedures for compliance with all state and federal laws,
policies related with safety and loss control, accident
prevention, and drug & alcohol abuse testing.
- Practices
and procedures to ensure quality of status reports, delineating
all OCIP costs incurred and credits obtained from
contractor/subcontractor bids and change orders.
- Practices
and procedures used for verification of bills and OCIP premium
adjustments.
Audits
will require interviews with representatives of the owner, GC,
contractors and subcontractors, broker, OCIP administrator, and the
insurer(s).
OCIP
- FAQs
An owner contemplating the implementation of an OCIP may
receive a number of questions from their own internal management and
the GC, who would be responsible for a significant portion of the
OCIP administration, and contractors and subcontractors. In
addition, there may be a series of questions from regulatory
agencies, such as OSHA, union officials, and from national and local
trade associations representing contractors and subcontractors that
would be enrolled in the OCIP. Some frequently asked questions
(FAQ’s) include:
- What’s the difference between an OCIP and a Wrap-Up?
The terms OCIP and wrap-up are frequently used interchangeably because
the underlying premise is relatively the same. Both have the same
insurance coverages, usually WC, GL, and an Umbrella, however, there
is a slight difference. The wrap-up concept had originally emerged
as a form of consolidated insurance program that placed the
responsibility for providing insurance coverage on the prime
contractor, or GC, for all its subcontractors. In this context, the
wrap-up would be considered a contractor controlled insurance
program (CCIP). In comparison, an OCIP provides similar coverage as
a CCIP, but the owner is the sponsor and provides insurance for all
parties. In other words, the owner takes total responsibility for
the insurance procurement, including direct payment of premiums, and
the management and administration of the entire program.
- How does an OCIP benefit an owner?
An owner benefits from an OCIP in many ways which include; cost
savings, more efficient project management and administration, more
effective safety and loss control programs, more opportunities for
MBE/WBE/DBE/SBE contractors and subcontractors, having direct
control of insurance coverage exclusions, obtaining higher insurance
limits and mitigating claim disputes. The primary advantage of an
OCIP is increased control, hence the name, Owner “Controlled”
Insurance Program. Other factors include obtaining a lower cost of
risk, resulting from cost reductions and protection from
catastrophic loss by obtaining higher limits of liability insurance
coverage.
- How much additional time will an OCIP require from an
owner’s management staff?
The estimated time expenditure will be more significant in the initial
stages of design and implementation of an OCIP. However, once an OCIP is up and running, the time required
for administration will be minimal, consisting mostly of responding
to coordination questions and reviewing periodic OCIP status reports
with the broker, OCIP administrator, and insurer.
- If an owner commits to an OCIP, can it revert back to a
conventional insurance program?
There are several reasons why an owner may want to dissolve an OCIP,
but the main reason is usually driven by economic factors as a
result of changes in insurance market conditions. Given the economic
volatility, as respects hard and soft insurance markets, if an OCIP
is implemented in a hard market and the market softens, the OCIP
will cost less than projected.
However, if an OCIP is implemented in a soft insurance market, which
usually will provide broader coverage, lower rates and higher
limits. If the market hardens, costs will increase, coverage may be
reduced and limits lowered. This economic cycle can make it
extremely difficult for an owner to provide the necessary insurance
coverage, which is a contractually stipulated requirement on all
construction projects.
In the event that the owner cannot provide the contractually required
insurance coverage, the OCIP may need to be dissolved. The
dissolution of the OCIP would entail the negotiation of contract
cost adjustments, including change order increases with contractors
and subcontractors currently enrolled in the OCIP. The magnitude of
increased construction cost would have a negative financial impact
on the project’s profitability.
·
Do all contractors and subcontractors who perform
work on the project have to participate and be enrolled in the OCIP?
Contractors or subcontractors that perform the majority of their work
away from the project site may be excluded from an OCIP. The reason
for this exclusion is primarily that the limited project site
exposure in the contractors or subcontractors contract results in
limited risk and exposure to jobsite injuries, claims and liability.
In addition, contractors and subcontractors should also be excluded
from an OCIP if their contract value is less than a certain amount.
It just isn’t practical from an administration standpoint to have
these types of contractors and subcontractors enrolled in the OCIP. Depending on the total construction cost of the project, a
good rule of thumb is to exclude contractors and subcontractors with
contract values less than $25,000 or $50,000, but these figures are
relative.
·
Do OCIPs provide an unfair competitive advantage to
contractors with poor loss experience, bidding on work against a
contractor with a good safety record?
Contractors
with poor loss experience usually expend a greater percentage of
revenue on the cost of insurance than contractors with good safety
performance and low loss experience.
Therefore, contractors with poor loss experience should have
higher insurance costs, higher total costs and higher construction
bids than a contractor with favorable loss experience.
By
removing insurance costs from construction bids, contractors with
favorable loss experience may lose a cost advantage. However, the
difference in contractors' bids created by differences in loss
experience is likely to be small when measured as a percentage of
construction bids. Also, by making insurance costs a neutral factor,
the bid competition is focused on more substantive issues, like
performance, quality of workmanship and safety.
In
addition, if a contractor is to develop the lowest bid, it will be
because of lower labor, material or other costs and not because of
lower insurance costs. This should be an advantage to the owner. As
an additional measure to eliminate any
advantage a contractor or subcontractor with poor loss experience
may have, some owners will not accept bids with workers compensation
EMRs exceeding a set level, e.g., 125%.
- Are
contractors and/or subcontractors loss-sensitive insurance
programs impaired by an OCIP, that it would cause them to have
less leverage with their own insurance carriers?
Loss-sensitive insurance programs, such as dividend plans and
retrospective rating plans, have two components, a fixed charge and
a variable charge. The variable charge is based on frequency and
severity of losses. When a contractor’s or subcontractor’s
projected payroll (the predominant rating base for the determination
of premium), is moved from their own insurance program to an OCIP,
the fixed charge may increase as a percentage of premium, as a
result of this reduction in payroll. If a substantial portion of the
premium is moved to the OCIP, the effect on a contractors or
subcontractors own insurance premium may ultimately result in a
higher fixed cost, but a lower variable cost.
An
OCIP may not be the best choice for a risk management program on all
projects, but an OCIP is a comprehensive insurance program that
warrants consideration for many single-site projects with total
construction values in excess of $100 million and portfolios of
smaller projects that aggregate to at least $50 million annually.
The trend over the last several years has lowered the minimum
threshold in each state for the use of wrap-ups. Consult your state insurance laws.
There are many ways to structure an OCIP program, but like everything
else in the construction industry, planning is a key element of any
successful program. An
OCIP provides an owner with some definite advantages over a
traditional insurance program; substantial savings potential,
broader insurance coverage, higher policy limits, more efficient
claims management, and better safety and loss control procedures.
Owners should structure an OCIP carefully with the help of a
competent risk management professional.
About the Author
David L. Grenier is President of C-Risk, Inc., a national
risk management consulting firm that provides risk management strategies and
solutions to construction industry clients. (phone:
503-228-0884, e-mail: david.grenier@c-risk.com,
or Web site: www.C-Risk.com). He specializes in construction risk management, contracts, insurance and wrap-up programs.
David has over 25 years experience in the construction industry. He has held senior-level project
management positions with some of the nation’s top engineering and construction
firms and was an insurance executive with several national insurance
companies.
David holds a BS in Construction Management from Syracuse University and a MBA in Finance,
Marketing, and Business Strategy from the University of Chicago Graduate School
of Business. He is currently a member of CFMA’s Colorado Chapter and serves on
CFMA’s Construction Industry Liaison Committee.
The information in this article, and all other articles provided by C-Risk, is intended for general information
purposes only and does not constitute, nor is it intended to constitute, legal advice. For legal advice, you
should always consult with the appropriate legal counsel in order to determine the laws that are applicable
to your specific circumstances.
|